In two decisions dated 17 September 2024 (case no. EnZR 57/23 and EnZR 58/23), the BGH recently ruled on the question of the balance sheet allocation in higher voltage levels in the event of an energy supplier default.

GermanyEnergy and Natural Resources

*Update on the decisions of the Düsseldorf Higher Regional Court of 2 March 2023 (Ref. 5 U 1/22 and 5 U 3/22)

What are the decisions about?

In two decisions dated 17 September 2024 (case no. EnZR 57/23 and EnZR 58/23), the BGH recently ruled on the question of the balance sheet allocation in higher voltage levels in the event of an energy supplier default. On appeal by the plaintiff and the defendant, the BGH amended and revised the respective previous decisions of the Düsseldorf Higher Regional Court (we reported).

What happened?

In the facts of the cases underlying the decisions, the planned supply to end consumers at the medium-voltage level was no longer possible due to the insolvency of their new electricity supplier. The end consumers then concluded short-term transitional supply contracts with their previous electricity supplier. However, these supply contracts were not registered with the responsible grid operator in good time due to a system error on

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from