The Melbourne Earthquake: How It Should Have Been Dealt With In An Australian Standard Construction Contract

On 22 September 2021, a magnitude 5.9 earthquake struck Victoria. Undoubtedly, this led many construction managers in Melbourne to review their contracts to assess who bears the risk for any damage caused.

AustraliaReal Estate and Construction

On 22 September 2021, a magnitude 5.9 earthquake struck Victoria. Undoubtedly, this led many construction managers in Melbourne to review their contracts to assess who bears the risk for any damage caused.

Ordinarily, Contractors carry the risk for all loss or damage which occurs during the works whilst they are managing the site with the exception of certain defined risks. During contract negotiations, both parties seek to future proof their contracts by anticipating events arising and allocating the risks of events, these risks should include the risk of earthquake and floods.

Force Majeure Clause

An example of such a provision is a force majeure clause. These clauses operate to provide parties contractual relief for loss, damage, claims, delays etc  resulting from unforeseeable events including environmental events, sometimes termed ‘acts of god', which can be defined under the contract. Such clauses often favour the Contractor, as the performing party

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from