On 22 September 2021, a magnitude 5.9 earthquake struck
Victoria. Undoubtedly, this led many construction managers in
Melbourne to review their contracts to assess who bears the risk
for any damage caused.
Ordinarily, Contractors carry the risk for all loss or damage
which occurs during the works whilst they are managing the site
with the exception of certain defined risks. During contract
negotiations, both parties seek to future proof their contracts by
anticipating events arising and allocating the risks of events,
these risks should include the risk of earthquake and floods.
Force Majeure Clause
An example of such a provision is a force majeure clause. These
clauses operate to provide parties contractual relief for loss,
damage, claims, delays etc resulting from unforeseeable
events including environmental events, sometimes termed ‘acts
of god', which can be defined under the contract. Such
clauses often favour the Contractor, as the performing party