Court of Appeal warning to payment claim respondents

Recent Queensland decision impacts the scope of matters that should be raised by respondents in payment schedules.

AustraliaReal Estate and Construction

Earlier this month, the Queensland Court of Appeal handed down a decision of critical importance to payment claim respondents. This is a significant decision that impacts on the scope of matters that should be raised by respondents in payment schedules.

You can read the full decision in Ausipile Pty Ltd v Bothar Boring and Tunnelling (Australia) Pty Ltd  [2021] QCA 223 here.

Facts

Bothar Boring and Tunnelling (Australia) Pty Ltd ('Bothar') engaged Ausipile Pty Ltd ('Ausipile') to carry out work associated with the installation of a pipe between Biggera Waters and South Stradbroke Island. Ausipile issued a payment claim for amounts that were still outstanding in respect of previous claims, as well as an amount for hiring a crane to Bothar. Bothar did not provide a payment schedule in response.