On 07 July 2020, the Ministry of Industry and Trade
("MOIT") issued Circular No. 16/2020/TT-BCT to amend and
supplement certain provisions of Circular No. 44/2-15/TT-BCT dated
09 December 2015 of the MOIT Minister on project development,
avoided cost tariff and standardized power purchase agreement for
biomass power projects.
In particular, this new Circular provides that investors be only
allowed to build on-grid biomass power investment projects, which
have been included in the approved Power Development Plan or
Provincial Power Development Plan.
In addition, feed-in-tariff for on-grid biomass power projects
will follow Decision No. 08/2020/QD-TTg dated 05 march 2020, which
increases the feed-in tariff for biomass co-generation heat power
to 7.03 US cents per kilowatt hour (up from 5.8 US cents), and for
other types of biomass projects to 8.47 US cents per kWh (up from
7.3 to 7.5 US cents depending on location).