Vietnam – Power Development Plan 8 – Implementation

Duane Morris LLP
Duane Morris LLP
Contributor
Explore more from Duane Morris LLP

On 26 January 2024, the Ministry of Industry and Trade (the "MOIT") delivers Letter No. 644/TTr-BCT ("Letter 644") to the Vice Prime Minister – Mr. Tran Hong Ha – regarding the proposal...

VietnamEnergy and Natural Resources

On 26 January 2024, the Ministry of Industry and Trade (the “MOIT”) delivers Letter No. 644/TTr-BCT (“Letter 644”) to the Vice Prime Minister – Mr. Tran Hong Ha – regarding the proposal for the issuance of the Implementation Plan for the National Power Development Master Plan VIII for the period 2021-2030, with a vision to 2050 (the “Implementation Plan”). We would like to highlight some key notes of the Letter 644 Implementation Plan as below:

(i) To approve the Implementation Plan in two (02) phases whereby the first phase will mainly cover the the list of important and prioritized power source and power grid projects together with the list of wind power projects, small hydropower, biomass power, electricity produced from waste, etc. which meets the criteria set out in the instructions, the types of power sources that meet the criteria to be developed. The second phase will cover the approval of the list of wind power projects, small hydropower, biomass power,

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

Disclaimer: This Alert has been prepared and published for informational purposes only and is not offered, nor should be construed, as legal advice. For more information, please see the firm's full disclaimer.

See more popular content from