After the Government Office's notification No. 402/TB-VPCP
dated 22 November 2019 on solar power FiT2 and auction scheme, the
MOIT has coordinated and consulted with EVN, MOF and MOJ to
finalize its draft solar power FIT2. On 31 December 2019, a final
draft submission letter from MOIT (with signature but no stamp)
(NB: no draft FiT2 PM Decision attached also) for FiT2 PM Decision
has been internally circulated. To our knowledge, this submission
letter and the draft FiT2 PM Decision would be duly executed and
submitted to the Prime Minister no later than COB next week. Please
kindly find below our highlights of this draft submission letter of
MOIT.
1. FIT2 Eligibility
The MOIT insisted that in order to be eligible for FiT2, solar
power projects must (i) have been in principle approved, and added
in the relevant power development planning, (ii) have signed PPAs
with EVN, (iii) be "under construction" prior to 23
November 2019, and (iv) reach COD by end of 2020.