RECENT DEVELOPMENT
Until June 2018, approx. 286 solar power projects of total
capacity of 19,300 MW have been submitted to the licensing
authorities to be supplement to the Power Master Plans, but only
100 projects have been approved (approx. 4,700 MW). We also note
that 90% projects are still in other licensing processes such as
application for investment registration license, construction
permit, etc.
At least 10 solar power projects that investors have signed PPAs
with EVN recently. By end of September 2018, the first solar energy
project will connect to the national power grid (35 MW in Hue
province).
With regards to the remaining projects have not yet been
included in the Power Master Plans, the Deputy PM Trinh Dinh Dung
has decided and instructed that MOIT must consider and approve to
addition if such solar energy projects satisfy one of the following
conditions: