This May 2022, the Ministry of Industry and Trade (MOIT)
publishes the second draft Decision for DPPA Pilot Program on its
website for stakeholders' review and comments. It is planned
that in the last quarter of 2022, MOIT will submit the final draft
for the Prime Minister's approval. Consequently, it is
expected that the Decision will be approved by the Prime Minister
in 2023.
Key points under the second draft DPPA Decision
Mandatory Eligibility Criteria:
1. Tariffed Customers: existing industrial customers taking
service at 22kV or higher
2. Project Size: larger than 30 MW
3. Technology Type: wind or solar PV
4. Renewable Energy Generating Company: owns power plants that
are either (i) ready to COD but are not eligible for FiT mechanism
or (ii) under construction, included in Power Development Plan and
identified investor and will achieve COD within 270 working
days