ARTICLE · 07 NOVEMBER 2022

Washington Supreme Court Finds One-Year Limitation Period In Construction Contract Unconscionable

Last week, the Washington Supreme Court issued a decision finding that a contractual one-year limitation period buried in a residential construction contract was unconscionable and void.

United StatesReal Estate and Construction

Last week, the Washington Supreme Court issued a decision finding that a contractual one-year limitation period buried in a residential construction contract was unconscionable and void. The case, Tadych v. Noble Ridge Construction, Inc., 2022 WL 15027140, provides important lessons for residential contractors and developers. The Tadychs entered into a written contract with Noble Ridge Construction to build a custom home. Noble Ridge Construction prepared the contract, which contained the following one-year limitation on claims:

Any claim or cause of action arising under this Agreement, including under this warranty, must be filed in a court of competent jurisdiction within one year (or any longer period stated in any written warranty provided by the Contractor) from the date of Owner's first occupancy of the Project or the date of completion as defined above, whichever comes first.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from