Virginia Supreme Court Undermines Effectiveness Of Flow-Down Provisions In Construction Agreements

At issue was a claim by Virginia Tech against Hensel Phelps (HP) for the alleged defective construction of a student health and fitness center completed in June 2000.

United StatesReal Estate and Construction

The Supreme Court of Virginia recently held in a construction case that typical flow-down provisions found in subcontracts are insufficient to pass through to the subcontractor, a general contractor's waiver of statute-of-limitations rights in the prime contract. The decision begs the question of whether a general contractor's waiver of other rights in a prime contract by the general contractor will flow through and bind a subcontractor by merely referring to the prime contract and/or incorporating it into the subcontract.

On November 3, 2016, the Supreme Court of Virginia held in the case of Hensel Phelps Construction Co. v. Thompson Masonry Contractor, that typical flow-down provisions found in subcontracts may not be sufficient to pass through to the subcontractor, a waiver of rights in the prime contract. The court also reiterated that indemnity clauses that even arguably indemnify against one's own negligence will be struck down in their entirety as void and

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from