U.S. District Court In Puerto Rico, Applying Connecticut Law, Considers Application Of Notice Requirements To Termination Of Joint Subcontractors

This action arose out of a surety’s claim for expenses incurred for correcting a subcontractor’s defective work.

United StatesReal Estate and Construction

Fed. Ins. Co. v. Empresas Sabaer, Inc.
2013 U.S. Dist. LEXIS 112930 (D.P.R. Aug. 9, 2013)

This action arose out of a surety's claim for expenses incurred for correcting a subcontractor's defective work. DTC Engineering and Constructors, LLC ("DTC") and the U.S. Army Corps of Engineers (the "Corps") entered into a contract for the design and construction of the Armed Forces Reserve Center at Fort Buchanan, located in Guaynabo, Puerto Rico. Federal Insurance Company ("Federal") and DTC subscribed to a payment and performance bond as surety and principal, respectively, naming the government as obligee. DTC subsequently entered into a subcontract (the "Subcontract") with Empresas Sabaer, Inc. ("Sabaer") and BBS Developers, S.E. ("BBS") (collectively the "Subcontractors"). The Subcontract provided that Sabaer was required to complete the work under Subcontract, while BBS was responsible for providing technical and economic support. United Surety and Indemnity

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from