U.S. District Court In Maryland Holds One-Year Statute Of Limitations Under Miller Act Did Not Commence Until After Required Testing Performed By Subcontractor

This action arose out of subcontractor’s claim for increased costs allegedly incurred as a result of delays on a federal government project.

United StatesReal Estate and Construction

United States of America ex rel D&M General Contracting, Inc v. Arch Ins. Co.
2013 U.S. Dist. LEXIS 111260 (D. Md. Aug. 5, 2013)

This action arose out of subcontractor's claim for increased costs allegedly incurred as a result of delays on a federal government project. NTVI Enterprises, LLC ("NTVI"), as general contractor, entered into an agreement with the government to upgrade the chiller plant for a National Security Agency facility (the "Project"). NTVI posted a labor and material payment bond for the Project (the "Bond") issued by Arch Insurance Company ("Arch"). NTVI then subcontracted with D&M General Contracting, Inc. ("D&M") to perform electrical work on the Project. Midway through the Project, D&M alleged that the sequence of its work was altered by the government resulting in an additional $206,674.07 in costs to D&M. Pursuant to the Miller Act, D&M filed suit against Arch, as surety, to recover under the Bond its increased costs allegedly incurred.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from