U.S. District Court In Georgia Considers Effect Of Releases Submitted With Applications For Payment, Notice Requirement As To Extra Work And Defective Specification Claims And No-Damage For Delay Provision

Pursuant to the subcontract, Duncan was to supply labor and material for the Project’s water distribution system.

United StatesReal Estate and Construction

United States of America ex rel Duncan Pipeline, Inc. v. Walbridge Aldinger Co. 2013 U.S. Dist. LEXIS 45982 ( S.D. Ga. Mar. 29, 2011)

This action arose out of a subcontractor's claim for additional compensation for extra work.. Walbridge Aldinger Co. ("Walbridge"), general contractor for the U.S. Army Corps of Engineers on construction project at Fort Stewart in Georgia (the "Project"), entered into a subcontract with Duncan Pipeline, Inc. ("Duncan"). Pursuant to the subcontract, Duncan was to supply labor and material for the Project's water distribution system. Duncan began its work in August 2009, and shortly thereafter, Walbridge ordered work that Duncan considered to be outside the scope of the subcontract, including installation of bell restraints, additional excavation work, and remobilization of crews because of interferences encountered during excavation. Duncan performed the allegedly extra work in August and September 2009, and submitted a bond claim to

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from