Update Your Construction Contract! Massachusetts Supreme Judicial Court Holds That Breach Of Contractual Indemnity Provision Is Not Barred By The Statute Of Repose

Conn Kavanaugh Rosenthal Peisch & Ford LLP
Explore more from Conn Kavanaugh Rosenthal Peisch & Ford LLP

Under the Massachusetts statute of repose, tort claims involving improvements to real estate generally must be initiated within six years of the improvement's opening to use.

United StatesReal Estate and Construction

Under the Massachusetts statute of repose, tort claims involving improvements to real estate generally must be initiated within six years of the improvement's opening to use.1 So, for example, if a worker suffers a jobsite injury as a result of an architect's design defect, the worker's claim against the architect is barred forever if it is not asserted within six years of the owner taking beneficial use of the project. Unlike statutes of limitations, this is true even if the claimant reasonably does not discover the negligence until after six years. The point of the statute is to give construction professionals certainty that they will not face claims – many of which involve complicated issues of fact – long after a project has wrapped.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from