As a response to an increasingly demanding market place, project
delivery methods have evolved from the more traditional methods of
design-bid-build, design-build, and construction-manager-at-risk
into what is known as Integrated Project Delivery
("IPD"). In the typical construction contract, each party
seeks to avoid and transfer risk to other parties. The IPD approach
employs a different philosophy—the project participants
accept and manage design and construction risks as a team. The pure
IPD method often does this with a single, multi-party contract that
is executed by the owner, general contractor, and designer. The
team members to a multi-party contract share financial risks and
rewards using a profit/incentive pool that is based upon measurable
project-outcomes. Team members collaborate on how the profit and
incentive pool is structured to ensure that each member is
accountable for its contribution to the project outcome. The goal
is to motivate each member in a