Subcontractor's Written "Expressions And Complaints" Demonstrate Disapproval, But Fail To Achieve Written Notice Of Additional Costs

Accordingly, the federal court dismissed the Subcontractor's inefficient labor claim on summary judgment.

United StatesReal Estate and Construction
Stites & Harbison PLLC
Stites & Harbison PLLC
Author LinkedIn connections

On February 4, 2019, the U.S. District Court for the District of Maryland in Hagen Constr. Inc. v. Whiting-Turner Contracting Co., No. JKB-18-1201, 2019 BL 36862 (D. Md. Feb. 4, 2019), held that written "expressions of frustration" and "general complaints" made by a subcontractor regarding alleged project mismanagement were insufficient to sustain a labor inefficiency claim for additional project costs against the general contractor.

Hagen Construction, Inc. ("Subcontractor") subcontracted with Whiting-Turner Contracting Co. ("General Contractor") for the construction of a pediatric medical center. The Subcontract provided the General Contractor was not responsible for costs related to additional work performed by the Subcontractor unless written notice of such additional work was provided to and approved by the General Contractor. The Subcontract also provided that, prior to approval of any payment application, the Subcontractor must provide executed lien waivers