On February 4, 2019, the U.S. District Court for the District of
Maryland in Hagen Constr. Inc. v. Whiting-Turner Contracting
Co., No. JKB-18-1201, 2019 BL 36862 (D. Md. Feb. 4, 2019),
held that written "expressions of frustration" and
"general complaints" made by a subcontractor regarding
alleged project mismanagement were insufficient to sustain a labor
inefficiency claim for additional project costs against the general
contractor.
Hagen Construction, Inc. ("Subcontractor")
subcontracted with Whiting-Turner Contracting Co. ("General
Contractor") for the construction of a pediatric medical
center. The Subcontract provided the General Contractor was not
responsible for costs related to additional work performed by the
Subcontractor unless written notice of such additional work was
provided to and approved by the General Contractor. The Subcontract
also provided that, prior to approval of any payment application,
the Subcontractor must provide executed lien waivers