To begin with, your lien will expire in 90 days from the date of recording. After that, your lien becomes null and void, completely unenforceable, and must be removed.

United StatesReal Estate and Construction

If you have recorded a mechanics lien in California, there are some important things you should know about the process moving forward.

Mechanics Liens Expire in 90 Days

To begin with, your lien will expire in 90 days from the date of recording. After that, your lien becomes null and void, completely unenforceable, and must be removed. You must either file a suit to foreclose the lien, get an extension, or release within those 90 days.

An extension may be obtained through a signed and notarized credit agreement with the owner, which must be recorded within the original 90-day window. The extension may be for up to 90 days, but in no case will extend beyond one year from completion of the project. No lawsuit can be filed during the extension, however. The best practice is to consult an attorney soon after recording the lien, and to pursue foreclosure (if necessary) well before the 90-day limit. During COVID-19, it is recommended that you record within 45 days of