A new study found slow payments to general contractors and
subcontractors cost $64 billion in 2019 – a nearly $25
billion increase from 2018 with general contractors added to the
report. The 2019 study, conducted by Rabbet (formerly Contract
Simply) through a partnership with Procore Technologies, collected
data from general contractors and subcontractors to evaluate the
rising costs of slow payments in construction. Rabbet's results
show the average 51-day payment turnaround is particularly hard on
subcontractors, and that the delay increases overall project costs
by more than 5%. While the report focuses primarily on the impacts
suffered by subcontractors as a result of slow payment (which
impacts include the cost of floating payments, higher risk of
bankruptcy, and other challenges), general contractors face the
same issues, in addition to the burden of mitigating secondary
effects such as added project costs and delays.