Sheetz v. County Of El Dorado: The Supreme Court's Latest Restraint On Development Fees

Davis Wright Tremaine LLP
Davis Wright Tremaine LLP
Contributor
Davis Wright Tremaine LLP

Davis Wright Tremaine LLP

Established in 1981, Davis Wright Tremaine's D.C. office features a team of lawyers that represent...

View firm profile
Explore more from Davis Wright Tremaine LLP

SCOTUS reverses California appellate decision, further restricting local government mitigation conditions on new development...

United StatesReal Estate and Construction

On April 12, 2024, Justice Amy Coney Barrett delivered the U.S. Supreme Court's opinion in Sheetz v. County of El Dorado, California, 601 U.S. 267, 144 S. Ct. 893 (2024). Sheetz concerned El Dorado County's imposition of $23,420 in traffic impact mitigation ("TIM") fees on George Sheetz's permit to site a manufactured home on his property. The County calculated the TIM fees for Sheetz's project based on a legislatively imposed rate schedule that took into account the type of development and its location within the County.

Sheetz paid the applicable TIM fee under protest, claiming that the fee did not make any type of individualized determination that the fee had any connection to or was fair in light of the impact of his development. Sheetz argued that the TIM fee ran afoul of the Takings Clause of the Fifth Amendment and did not accord with the "essential nexus" and "rough proportionality" requirements imposed on development conditions under the landmark cases of