Businesses turn to Sheppard to deliver sophisticated counsel to help clients move ahead. With more...

View firm profile
Explore more from Sheppard

Two weeks ago, the United States Supreme Court issued its decision in PPL Montana v. Montana. The Court held that the Supreme Court of Montana had incorrectly determined that certain segments of the Upper Missouri, Madison, and Clark Fork Rivers were "navigable" at the time of statehood.

United StatesReal Estate and Construction

Two weeks ago, the United States Supreme Court issued its decision in PPL Montana v. Montana. The Court held that the Supreme Court of Montana had incorrectly determined that certain segments of the Upper Missouri, Madison, and Clark Fork Rivers were "navigable" at the time of statehood. The Court therefore set aside the Montana court's determination that title to the beds of those rivers passed to the state upon statehood under the equal footing doctrine and remanded the case to the Montana Supreme Court for further proceedings consistent with the Court's opinion.

Background

PPL Montana is a power company that owns and operates hydroelectric dams built on the beds of the Upper Missouri, Madison, and Clark Fork Rivers in Montana. PPL holds federal licenses for its facilities and pays rent to the United States for its use of the riverbeds.