In Metcalf Construction Company v. United States,
the United States Court of Appeals for the Federal Circuit added
further support for contractors' reliance on owner provided
geotechnical data. 2014 U.S. App. LEXIS 2515, 2014 WL 519596
(Fed. Cir. Feb. 11, 2014). The decision dealt, in part, with
the federal government's standard differing site conditions
clause, 40 CFR 52.236-2; however, the decision may have some impact
beyond federal contracts since many other standard contracts employ
similar language.
Metcalf Construction Company was the successful bidder on a
contract to design and build 188 housing units at Marine Corp Base
Hawaii. The Government provided Metcalf and the other bidders
with "preliminary" soils information as part of the
request for proposals. The bidders, however, were instructed
to conduct their own independent investigation of the site.
One wise bidder submitted a pre-bid question asking:
"This requires an independent investigation