ARTICLE · 08 FEBRUARY 2001

Real Estate Newsletter - Second Quarter 2000

United StatesReal Estate and Construction
Eric P Gonchar
Eric P Gonchar

Construction In Manhattan Causes Delays For Closing

Developers in Manhattan have never been so busy building new condominiums. Construction of the Empire, Bridge Tower, Trump United Nations Plaza, Textile Building, Chelsea Mercantile, The Ritz Carlton Downtown, The Park Laurel, among others, are well underway and some are even complete. But buyers beware! A closing for these apartments cannot be completed until the NYC Building Department has at least issued a "temporary certificate of occupancy."

The "TCO" is a formal document issued by the Buildings Department which essentially acknowledges that the apartments are ready for residential occupancy (i.e. bathrooms and kitchens have been installed, etc.) Apartments in some buildings have been completed but because a TCO has not been issued, the closing cannot occur. This can result in delays which can ultimately cause a purchaser’s loan commitment or interest rate to expire. For building’s where construction is just commencing,

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from