ARTICLE · 13 AUGUST 2021

Property Owners Can Push The Issue Under Illinois Mechanic's Lien Law

The demand must then be sent to the lien claimant via registered or certified mail, return receipt requested, or by personal service.

United StatesReal Estate and Construction

Introduction

This past March, in CB Construction & Design, LLC v. Atlas Brookview, LLC, et al., the Illinois First District Appellate Court recognized a property owner's ability to significantly shorten the time for a mechanic's lien claimant to bring suit to enforce the lien.

In general, under the Illinois Mechanics Lien Act (770 ILCS 60/0.01 et seq.) (the "Act"), a lien claimant must commence a suit and join necessary parties within two years after the completion of the contract. However, under Section 34 of the Act, at any time prior to initiation of an enforcement suit, a property owner may issue a written demand to the claimant directing claimant to file suit within 30 days, or else lose the ability to enforce the lien.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from