Picerne Construction Corp. v. Castellino Villas (Feb. 18, 2016, C071197)

Sheppard
Sheppard
Contributor
Sheppard

Sheppard

Businesses turn to Sheppard to deliver sophisticated counsel to help clients move ahead. With more...

View firm profile
Explore more from Sheppard

The Third District Court of Appeal recently held that completion under the mechanics lien statute requires actual completion of the work of improvement, meaning completion of the entire structure or scheme of improvement as a whole.

United StatesReal Estate and Construction

The Third District Court of Appeal recently held that completion under the mechanics lien statute requires actual completion of the work of improvement, meaning completion of the entire structure or scheme of improvement as a whole, in Picerne Construction Corp. v. Castellino Villas (Feb. 18, 2016, C071197).*  In doing so, the Court resolved an ambiguity developed through case law by acknowledging the abrogation of authority that permitted completion to be found where only "trivial imperfections" to the work of improvement remained.

In Picerne, Picerne, the general contractor, and Castellino Villas, a single purpose LLC owner, entered into an agreement where Picerne would build an apartment complex called Castellino Villas in Elk Grove, California (City) that consisted of eleven apartment buildings, separate garages, a clubhouse, and other facilities.  Relevant dates related to the Court's analysis were:  (1) the City issued certificates of occupancy on separate