Last week, a rural Texas county enacted a one-year moratorium on data center construction, potentially imperiling as many as eight planned projects in the county. The action in Texas adds to a growing number of examples across the United States in which public opposition has the potential to materially affect data center projects. Given current public sentiment, stakeholders should continually and proactively recalibrate their mitigation strategies and deploy multidisciplinary, geographically fluent teams to anticipate and manage project risk.
Hill County Moratorium
With an estimated 400 data center projects either in development or operating statewide, Texas has been seen as an ideal location for developers. Texas aligns well with core siting criteria for hyperscale data centers—power, land, cost, and a friendly regulatory environment. Given the state’s preeminence in data center development, a recent decision in Hill County, Texas, is garnering particular attention. There, by a