ennsylvania Superior ruled that the commonwealth's prompt
payment act, the Contractor and Subcontractor Payment Act, 73 P.S.
§ 501 et seq. (CASPA), applies to mixed use
construction contracts even when such contracts include residential
construction in their scope that would not otherwise be governed by
CASPA. Indeed, in El-Gharbaoui v. Ajayi, the
appellate court ruled, in a decision marked for publication, that
CASPA applied to a contract for renovation to a building that
contained a daycare facility, a church, and two residential units.
No. 3057 EDA 2019, 2021 WL 3046856 (Pa. Super. Ct. July 20,
2021).
In Ajayi, appellant general contractor sued
appellee owners for breach of contract and penalties and
attorney's fees under CASPA for its work a on a
commercial/residential mixed use construction
project. Id. at *3. In a previous action, appellant
successfully foreclosed on its mechanics' lien and alleged, in
the present matter, appellees were collaterally estopped