ARTICLE · 26 SEPTEMBER 2017

Non-Breaching Party May Choose Between Liquidated Damages And Actual Damages If The Contract So Allows

The Supreme Court of Colorado has held that a contractual provision that gives a non-breaching party the option of choosing between recovery of liquidated damages and pursuing actual damages...

United StatesReal Estate and Construction

The Supreme Court of Colorado has held that a contractual provision that gives a non-breaching party the option of choosing between recovery of liquidated damages and pursuing actual damages is enforceable so long as the two remedies are exclusive. Ravenstar v. One Ski Hill Place, 2017 CO 83. The dispute in Ravenstar was over the failure of certain buyers to close on the purchase of condominium units. After the buyers breached, the developer/seller, kept their deposits as liquidated damages as permitted by the purchase and sale agreements.

The buyers sued for the return of their deposits, arguing that the liquidated damages provision in the agreements was unenforceable because it gave the developer/seller the option of pursuing actual damages. The agreements provided in relevant part as follows:

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from