Effective January 1, 2026: Time to Update Your Contracts
If your firm is involved in private construction in California,
a fundamental change in payment security is coming. Effective
January 1, 2026, for all contracts entered on or after that date,
Senate Bill 61 (creating Civil Code §8811) will cap retention
on most private works projects at a mandatory 5%.
This aligns private projects with the standards long applied to
public works in the state and marks the end of the traditional 10%
retainage practice.
The New Rules: What Everyone Needs to Know
The core of the new law is simple: You cannot withhold more than
5%.
- The Cap: Owners, direct contractors, and subcontractors at
every tier are prohibited from withholding more than 5% of any
progress payment as retention. The total retention proceeds
withheld also cannot exceed 5% of the total contract price.