ARTICLE · 19 NOVEMBER 2025

No More 10% Retainage: California Mandates 5% Retention Cap On Private Construction Projects

If your firm is involved in private construction in California, a fundamental change in payment security is coming. Effective January 1, 2026...

United StatesReal Estate and Construction

Effective January 1, 2026: Time to Update Your Contracts

If your firm is involved in private construction in California, a fundamental change in payment security is coming. Effective January 1, 2026, for all contracts entered on or after that date, Senate Bill 61 (creating Civil Code §8811) will cap retention on most private works projects at a mandatory 5%.

This aligns private projects with the standards long applied to public works in the state and marks the end of the traditional 10% retainage practice.

The New Rules: What Everyone Needs to Know 

The core of the new law is simple: You cannot withhold more than 5%.

  • The Cap: Owners, direct contractors, and subcontractors at every tier are prohibited from withholding more than 5% of any progress payment as retention. The total retention proceeds withheld also cannot exceed 5% of the total contract price.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from