NJ Supreme Court Clarifies When Causes Of Action For Construction Defects Accrue

The New Jersey Supreme Court recently held that the statute of limitations for construction defects begins to run when any owner in the chain of title knew or should have known of the defects.

United StatesReal Estate and Construction

The New Jersey Supreme Court recently held that the statute of limitations for construction defects begins to run when any owner in the chain of title knew or should have known of the defects. The case centered on The Palisades at Fort Lee, a condominium project originally developed as a rental property.

Palisades A/V Acquisitions Co. LLC (A/V) developed the condominium project in question. Work was substantially completed on May 1, 2002, and A/V operated the project as a rental property for approximately two years. In 2004, the property was sold and the new owner began the process of converting the property to condominiums, acting as the sponsor of the conversion.

In connection with the conversion process, an engineering report dated October 1, 2004, (the 2004 Report) was prepared that determined the structure to be in generally good condition. The conversion process also included the establishment of The Palisades at Fort Lee Condominium Association (the