The amount of a mechanic’s lien in California is generally the lesser of: 1) the reasonable value of the work; or 2) the price agreed upon in the lien claimant’s contract.

United StatesReal Estate and Construction

The amount of a mechanic's lien in California is generally the lesser of: 1) the reasonable value of the work; or 2) the price agreed upon in the lien claimant's contract. But does the same measure apply if a lien defendant was not a party to the contract? In Appel v. Superior Court of Los Angeles County, 214 Cal. App. 4th 329 (2013), the appellate court clarified that the same measure does apply.

In Appel, a defendant, the developer of a condominium project, admitted it had no assets. Six weeks before trial, however, it settled out of the case by stipulating to a judgment it apparently couldn't pay and granting a change order to the general contractor plaintiff. The change order purported to raise the contract price from $81 million to $95.5 million. The remaining defendants were condominium owners who were not parties to the general contract. They argued the change order was collusive. They intended to present evidence of what they contended was the "true" contract