Those who contribute labor or materials to construction
projects have special lien rights peculiar to the industry. In the proper
circumstances contractors, subcontractors and suppliers have the right to a
mechanic's lien -- a security interest in the real property under improvement.
If the lien claimant (e.g., a supplier who provided materials to the
project) is not paid, the mechanic's lien can be foreclosed, thereby securing
payment.
When the property owner is insolvent, a mechanic's lien may offer the only opportunity for payment. However, if the lien has not been
properly perfected, or if enforcement proceedings are managed incorrectly, the
remedy of foreclosure is not available. To perfect and enforce a mechanic's lien
the claimant must take whatever steps the law requires in the state where the
project is located. In California, this means that a preliminary 20-day notice
normally must be given, and, at the appropriate time, a claim of lien must be
recorded. Within