ARTICLE · 24 SEPTEMBER 2014

Mechanics Lien Subordination: Illinois Further Limits Construction Lenders’ Ability To Ensure Priority Against Mechanics Liens

Sheppard
Sheppard
Contributor
Sheppard

Sheppard

Businesses turn to Sheppard to deliver sophisticated counsel to help clients move ahead. With more...

View firm profile
Explore more from Sheppard

On July 16, 2014, Illinois enacted Public Act 98-764 (Senate Bill 3023) ("SB 3023"), which amends the Illinois Mechanics Lien Act (770 ILCS 60/ et seq.) (the "Act") to prohibit subordination of mechanics liens on Illinois construction projects, unless such subordination is to a construction mortgage lien made after 50% of the construction loan has been disbursed to fund construction costs.

United StatesReal Estate and Construction

On July 16, 2014, Illinois enacted Public Act 98-764 (Senate Bill 3023) ("SB 3023"), which amends the Illinois Mechanics Lien Act (770 ILCS 60/ et seq.) (the "Act") to prohibit subordination of mechanics liens on Illinois construction projects, unless such subordination is to a construction mortgage lien made after 50% of the construction loan has been disbursed to fund construction costs.

SB 3023 represents continuation of a multi-year dispute in the Illinois legislature that arose from the Illinois Supreme Court's decision in LaSalle Bank N.A., v. Cypress Creek, 242 Ill. 2d. 231 (2011).  InCypress Creek, the Illinois Supreme Court held that under the value "enhancement" provisions of Section 16 of the Act, a mechanics lien claimant in a foreclosure proceeding was only entitled to lien priority to the extent that each such mechanics lien claimant's work improved the property.  In such case, a construction mortgage lender would receive "credit" for the value of work

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.