On April 12, 2016, the Missouri Court of Appeals held, for the first time, that contractors who have performed work for shopping mall tenants may have mechanic's lien rights on the entire mall if the tenant fails to pay.

United StatesReal Estate and Construction

On April 12, 2016, the Missouri Court of Appeals held, for the first time, that contractors who have performed work for shopping mall tenants may have mechanic's lien rights on the entire mall if the tenant fails to pay. The case, Crafton Contracting Co. v. Swenson Construction Co., gives contractors and subcontractors an opening to more effectively enforce liens for improvements made on mall property.

The Crafton court held that when a mall lease requires a tenant to make improvements "of a substantial and permanent nature" to its retail store, the tenant, in making such improvements, becomes an agent of the mall for purposes of subjecting the mall to a lien. The Crafton court noted that "where the improvements are required and completed under the control of the [mall] owner with the view of improving the property," it is immaterial whether the mall owner ultimately benefits financially from the tenant build out. Applying this reasoning to the facts of Crafton, the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from