Louisiana Public Entities Can No Longer Withhold Contested Liquidated Damages

Jones Walker LLP
Jones Walker LLP
Contributor
Jones Walker LLP

Jones Walker LLP

Jones Walker LLP is among the 140 largest law firms in the United States serving local, regional,...

View firm profile
Explore more from Jones Walker LLP

Louisiana Act 255 fundamentally shifts the leverage dynamic on public construction projects by prohibiting owners from withholding payment over disputed liquidated damages. Under the new law, public entities must pay contractors first and pursue delay claims through separate litigation, with significant financial consequences including attorney fee recovery and daily interest penalties for both parties. How will this statutory codification of prior court rulings reshape payment practices and dispute resolut

United StatesReal Estate and Construction

Act 255 changed Louisiana’s public prompt-payment rules, and on public projects it changes the balance of leverage in a real way. It took effect May 15, 2026.

The core change: A public owner can no longer hold back liquidated damages the contractor disputes. If the owner believes it is owed delay damages, it has to pay the contractor first and pursue the claim in a separate lawsuit. The one exception is narrow — flood protection and integrated coastal projects — and it opens only after the standard 45-day payment window closes.

This is less a reversal than a codification. Louisiana courts had previously ruled that a public entity could not sit on a contractor’s retainage over an unproven delay claim, and that a contract clause purporting to allow it did not override the duty to pay. Act 255 now writes that into the statute and names contested liquidated damages directly, so the outcome no longer turns on how a court may read the older law.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from