Florida Court Rules on Statute of Limitations for Claims Against Subcontractors Under Performance Bonds

In a case with potential implications for owners, contractors and subcontractors in Florida, the Third District Court of Appeal has issued a ruling that significantly affects the time period during which claims can be brought against subcontractors under performance bonds.

United StatesReal Estate and Construction

Michael Milne is an Associate in our Orlando office
Kenneth Richie is a Partner in our Orlando office

In a case with potential implications for owners, contractors and subcontractors in Florida, the Third District Court of Appeal has issued a ruling that significantly affects the time period during which claims can be brought against subcontractors under performance bonds.

In BDI Construction Company v. Hartford Fire Insurance Co., 995 So. 2d 576 (Fla. 3rd DCA 2008), the School Board of Miami-Dade County contracted with a contractor for the construction of a senior high school. The contractor subcontracted with BDI Construction, which in turn hired a sub-subcontractor named E&F Contractors, Inc. for the stucco and drywall work. As the sub-subcontractor's surety, Hartford Fire Insurance issued a performance bond for the work naming BDI Construction as the obligee, or beneficiary.