This fall the Georgia Court of Appeals ruled against a
subcontractor who failed to file an affidavit of non-payment or a
claim of lien within sixty (60) days of signing a statutory lien
waiver. In ALA Construction Services, LLC v. Controlled
Access, Inc. 833 S.E.2d 570 (2019), Controlled Access, in
the normal course of business, signed an interim statutory lien
waiver in accordance with O.C.G.A. § 44-14-366. Controlled
Access was not paid. Controlled Access did not file an affidavit of
non-payment or a claim of lien within 60 days of submitting its
statutory lien waiver.
In reversing the trial court order’s granting judgment in
favor of Controlled Access, the Court of Appeals ruled that
pursuant to the language contained in the lien law statutes, one is
conclusively deemed to be paid in full if the party fails to file
an affidavit of non-payment or a claim of lien within the 60 days
of submitting the statutory lien waiver. Thus, the rights of the
party to