Filing Affidavit Of Non-Payment Within 60 Days Of Signing Statutory Lien Waiver Is Critical In Georgia Construction Contracts

This fall the Georgia Court of Appeals ruled against a subcontractor who failed to file an affidavit of non-payment or a claim of lien within sixty (60) days of signing a statutory lien waiver.

United StatesReal Estate and Construction

This fall the Georgia Court of Appeals ruled against a subcontractor who failed to file an affidavit of non-payment or a claim of lien within sixty (60) days of signing a statutory lien waiver. In ALA Construction Services, LLC v. Controlled Access, Inc. 833 S.E.2d 570 (2019), Controlled Access, in the normal course of business, signed an interim statutory lien waiver in accordance with O.C.G.A. § 44-14-366. Controlled Access was not paid. Controlled Access did not file an affidavit of non-payment or a claim of lien within 60 days of submitting its statutory lien waiver.     

In reversing the trial court order’s granting judgment in favor of Controlled Access, the Court of Appeals ruled that pursuant to the language contained in the lien law statutes, one is conclusively deemed to be paid in full if the party fails to file an affidavit of non-payment or a claim of lien within the 60 days of submitting the statutory lien waiver. Thus, the rights of the party to

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from