On September 26, 2024, Judge Phillip Brimmer of the U.S. District Court for the District of Colorado issued an unpublished opinion holding that Colorado's Construction Anti-Indemnification Statute.

United StatesReal Estate and Construction

On September 26, 2024, Judge Phillip Brimmer of the U.S. District Court for the District of Colorado issued an unpublished opinion holding that Colorado's Construction Anti-Indemnification Statute, C.R.S. § 13-21-111.5(6)(b) applies to repair work conducted near a well site and that certain indemnification provisions requiring a contractor to indemnify an operator for its own negligence under a master service contract ("MSC") were void as a result. BKV Barnett, LLC v. Elec. Drilling Tech., LLC, Case No. 23-CV-00139-PAB-SBP (D. Colo. Sept. 26, 2024). The following summarizes key aspects of this decision.

Case Background: BKV Barnett, LLC ("BKV") is an operator of an onshore oil and gas well site in Texas that lost power due to a lightning strike. BKV contracted with Electric Drilling Technologies, LLC ("EDT") to supply electric power to the well site and to provide related rental equipment pursuant to an MSC.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from