ARTICLE · 22 AUGUST 2025

Failure To Timely Join An Indispensable Party Identified After CEQA Suit Was Filed Mandated Dismissal

The Court of Appeal held upheld the dismissal of a CEQA action for failure to timely name a developer that became a real party in interest during the pendency of the action. Citizens for a Better Eureka v. City of Eureka, 111 Cal.App.5th 1114 (2025).

United StatesReal Estate and Construction

The Court of Appeal held upheld the dismissal of a CEQA action for failure to timely name a developer that became a real party in interest during the pendency of the action.Citizens for a Better Eureka v. City of Eureka,111 Cal.App.5th 1114 (2025).

On April 4, 2023, the City of Eureka adopted a resolution authorizing the removal of a public garage in order to facilitate development of affordable housing, relying on a Class 12 exemption under CEQA for the disposal of surplus government property.

On May 5, Petitioner CBE filed a petition challenging the April 4 Resolution, alleging the City piecemealed the project—which it characterized as including both removal of the garage and development of affordable housing—such that the project did not qualify for a Class 12 exemption.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from