ARTICLE · 15 JANUARY 2015

Fabricator/Erector Right To Pay For Extra Work Delayed By Legal Morass

A recent intermediate appellate court decision demonstrates how a complex legal relationship can significantly prejudice a fabricator/erector’s entitlement to its contract balance and payment for extra work.

United StatesReal Estate and Construction

A recent intermediate appellate court decision demonstrates how a complex legal relationship among an owner/developer, a design/builder, and a construction manager-at-risk can significantly prejudice a fabricator/erector's entitlement to its contract balance and payment for extra work. The situation is an obvious, continuing nightmare for the fabricator and erector involved – companies that tried to follow their contracts "by the book;" but, some eight years after the work was complete, they still have not been paid. It provides a number of lessons and warnings for those involved in the fabricated structural steel industry in the United States.
The decision is not yet final and the fabricator/erector's battle is not yet over; so stay tuned. A summary of what has occurred so far and some lessons to be learned are set out below.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from