Equity Applies in Fashioning Mechanics Lien Remedies in Illinois

United StatesReal Estate and Construction
James Carr
James Carr

Rules of equity, though irrelevant to determining the existence of lien rights, can be applied in fashioning a remedy once the lien right is established. Although the Illinois Mechanics Lien Act is to be construed liberally, in keeping with its remedial purpose, few cases have considered the judicial standards for fashioning appropriate remedies. A recent Illinois appellate court decision, however, provides guidance in applying equitable principles under the Act. Westcon/Dillingham Microtunneling v. Walsh Const., 747 N.E. 2d 410 (Ill. App. 2nd Dist. 2001).

A subcontractor, Westcon/Dillingham Microtunneling (Westcon), brought a mechanics lien action against public funds on a county sewer project. Westcon alleged it encountered differing site conditions during the sewer installation. Westcon sought payment of its subcontract retention as well as costs attributed to adverse subsurface conditions. After retention funds were released to Westcon, another subcontractor, Glenbrook

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from