In the last issue of Pipeline, we reported on actions by the Zoning Commission of the District of Columbia at the behest of the Office of Planning to temporarily curb the development of telecommunications related facilities in the District of Columbia (affectionately called "Electronic Equipment Facilities" by the Office of Planning). In December of 2000, several developers and users petitioned the Zoning Commission for special exception relief to permit those Electronic Equipment Facilities ("EEFs") in the pipeline to go forward. Those requests were made pursuant to a process set forth in the Emergency Rulemaking adopted by the Zoning Commission in October and November of 2000.
Of the five requests for special exception relief made at that time, four were heard by the Zoning Commission on December 18, 2000 and were granted relief as bench decisions by the Commission. Each approval came with conditions – conditions that require EEF buildings to have full building lighting to give an