ARTICLE · 05 OCTOBER 2018

Doing Business With The NYC SCA: Absence Of Notice Of Direction Does Not Preclude Claim

The processing of change orders by many New York public agencies can be challenging. This is particularly so with the NYC School Construction Authority (SCA).

United StatesReal Estate and Construction

The processing of change orders by many New York public agencies can be challenging. This is particularly so with the NYC School Construction Authority (SCA).

For example, when it comes to extra or additional work, SCA personnel often informally direct the work to be performed either verbally at the project level or in meeting minutes or by email. However, this procedure often degenerates into an adversarial demand to perform, threats of back charges, or even threat of default and a premature calling upon a contractor's surety.

The "disputed work" provision of the standard SCA contract appears to leave the contractor with little alternative but to promptly perform the disputed work in the hopes of being fairly compensated later. Inconsistently, however, the SCA contract speaks of the contractor's need for a written Notice of Direction (NOD) in order to pursue a claim.