Share on LinkedInShare on LinkedIn

ARTICLE · 02 DECEMBER 2016

Court Rejects Contractor's Mechanic's Lien Because Of ‘Intent'

The Illinois Court of Appeals' recent decision in AUI Construction Group, LLC v. Vaessen highlights the need for careful planning in structuring development agreements, construction contracts...

United StatesReal Estate and Construction

The Illinois Court of Appeals' recent decision in AUI Construction Group, LLC v. Vaessen highlights the need for careful planning in structuring development agreements, construction contracts, and the use of an easement as opposed to a lease. The appeal in AUI Construction Group addressed a subcontractor's mechanic's lien claim against a landowner, although those two litigants were at opposite ends of multiple layers of contracts. The layers of contracts are explained below.

The case arose out of a wind farm project. The land at issue, once farmland, is owned by Louis and Carol Vaessen. The Vaessens entered into an agreement with wind farm developer GSG 7, resulting in an easement in favor of the developer to install and operate wind energy systems. The agreement required the developer to pay the Vaessens $7,500 per year. The developer contracted with Clipper to supply both the wind turbine and the tower to support the turbine. Clipper built the turbine itself, but

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from