ARTICLE · 30 JANUARY 2014

Court of Federal Claims Holds Contract Term Prescribing Adjustment For Variances Does Not Bar Claim For Breach Of Contract Based On Negligent Estimates

This action arose out of a contractor’s claim for additional compensation for unanticipated work.

United StatesReal Estate and Construction

Ravens Group, Inc. v. United States
2013 U.S. Claims LEXIS 979 (Fed. Cl. 2013)

This action arose out of a contractor's claim for additional compensation for unanticipated work. The U.S. Army (the "Government") solicited private contractors to provide the maintenance and repair services for General and Flag Officers Quarters ("GFOQ") at Fort Myers, Virginia and Fort McNair, Washington D.C. GFOQ is military housing specifically designated for senior officers of the military and their families. Traditionally, the Government used "in-house" personnel to respond to the majority of the maintenance and repair service calls at GFOQ housing. The solicitation from private contractors marked a new initiative in which the service calls at these two bases would be handled exclusively by a private contractor.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from