Court Holds Subcontractor Cannot Lien For Temporary Sidewalk Shed And Scaffold

An owner of a Manhattan 12-story building hired a contractor to perform façade repairs. The contract required a pedestrian sidewalk shed and scaffolding for the repairs,...

United StatesReal Estate and Construction

An owner of a Manhattan 12-story building hired a contractor to perform façade repairs. The contract required a pedestrian sidewalk shed and scaffolding for the repairs, both to be removed upon completion. A subcontractor furnished and installed the shed and scaffold, to be paid on a monthly basis, and eventually removed them. The sub was not paid so it filed a mechanics lien. Because the shed and scaffold were held to be temporary structures, not a permanent improvement, the subcontractor's mechanics lien was vacated. In the Matter of W 54-7 LLC v Interstate S&S Corp., First Department 11-3-2022.

In New York, one can file a mechanics lien for performing labor or furnishing material for the improvement of real property. The improvement must be of a permanent character. Window shades, soap dishes, and cutting a lawn are not permanent. Constructing a building is. Much lies between these poles. For example, NYC subway construction contracts sometimes call

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from