Complex construction cases are rarely tried to a jury in
Kentucky. Following eight years of litigation and a lengthy
jury trial, last Friday, the Kentucky Court of Appeals issued an
unpublished opinion that vacated a judgment and remanded the
case. Dugan & Meyers Construction Co v. Superior
Steel, Inc., et. al., 2012-CA-000440-MR
The Court of Appeals' decision highlights the time-consuming
frustrations of litigating construction disputes and the
significance of industry standard contract clauses for every tier
of project participants. As the concurring opinion
wrote: "each party to this case has remedies under its
respective contract, although some contracts provide better
remedies than others. The parties negotiated those contract
relationships and generally should be bound by those
terms."