Contractor Loses Effort To Bind Remote Home Purchaser To Arbitration Clause

On December 8, 2020, in Taylor Morrison of Texas, Inc. v. Kohlmeyer, a Texas Court of Appeals rejected a contractor's appeal of a trial court order...

United StatesReal Estate and Construction

On December 8, 2020, in Taylor Morrison of Texas, Inc. v. Kohlmeyer, a Texas Court of Appeals rejected a contractor's appeal of a trial court order denying the contractor's motion to compel arbitration in a home construction defect dispute. The appellate court concluded that the theories of direct benefits estoppel and implied assumptions did not permit the contractor to bind a subsequent purchaser to mandatory arbitration required under the original purchase agreement.

In 2013, the contractor, Taylor Morrison, executed a purchase agreement with a homeowner for the construction of a new home in League City, Texas. The purchase agreement included a mandatory arbitration provision and provided that it may not be assigned without the prior written consent of Taylor Morrison. In March 2016, the homeowner sold the house, and, later that year, the property was sold again to the Kohlmeyers. In 2018, the Kohlmeyers sued Taylor Morrison “asserting that the house had

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from