Contractor Liable For Liquidated Damages Because It Failed To Properly Seek Extension Of Time

The Fifth Appellate District of the California Court of Appeal recently issued an opinion that has important implications to all stakeholders in California's construction industry.

United StatesReal Estate and Construction

The Fifth Appellate District of the California Court of Appeal recently issued an opinion that has important implications to all stakeholders in California's construction industry. In Greg Opinski Construction, Inc. v. City of Oakdale, Nos. F060219, F060727, 2011, 2011 WL 4625304 (Cal. Ct. App. Oct. 6, 2011), the California Court of Appeal held that where a contract contains specific requirements for obtaining an extension of time, and a contractor fails to comply with those requirements, it is barred from later contesting its liability for any project delays.

The Greg Opinski opinion has significant implications for the California construction industry. Principally, the opinion means that contractors must timely submit claims for alleged owner-caused delays in compliance with the terms of their contracts, or else risk suffering the fate of the general contractor in this case and be barred from contesting liability for delayed completion. The opinion also means, as

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from