Abandonment is a well-known concept on construction projects
in California. It generally arises in different situations. One
example is when the project's design is so deficient that
the contractor performs a massive amount of change orders and
extra work. This may qualify as contract abandonment, resulting
in the contractor or subcontractor recovering damages against
the owner or prime contractor on a quantum meruit theory (with
the exception set forth below).
Another example is when a contractor wrongfully ceases
working and leaves the project. This is project
abandonment.
Several judicial decisions have established the principle of
contract abandonment, giving rise to its use in construction
litigation. In C. Norman Peterson Co. v. Container Corp. of
America (1985) 172 Cal.App.3d 628, the court held that
when owner imposed changes (or prime contractor imposed changes
vis-à-vis a subcontractor)