ARTICLE · 25 JUNE 2018

California Supreme Court Holds That Contractors May Not Unreasonably Withhold Retention Payments

Until recently, there has been a split in the courts of appeal in California regarding the extent to which contractors are excused from the prompt payment requirement for retentions.

United StatesReal Estate and Construction
Lewis Brisbois Bisgaard & Smith LLP
Lewis Brisbois Bisgaard & Smith LLP
Author LinkedIn connections

Until recently, there has been a split in the courts of appeal in California regarding the extent to which contractors are excused from the prompt payment requirement for retentions. One rule permitted contractors to withhold retention payments to subcontractors if there was any good faith dispute between them, whether or not the dispute was directly related to the work for which the retention was given. The other rule limited a contractor's ability to withhold retention payments to good faith disputes which specifically involved the work for which the retention was held.

At the heart of the issue was the interpretation of California Civil Code Section 8814. The statute states:

(a) If a direct contractor has withheld a retention from one or more subcontractors, the direct contractor shall, within 10 days after receiving all or part of a retention payment, pay to each subcontractor from whom retention has been withheld that subcontractor's share of the payment.